Gallery Project Updates
Upcoming 2 week schedule highlights - October 19 - 30
-
Construction coordination meetings occur every Wed. at 2pm on site.
-
October: Heating ductwork, insulation, rough plumbing and electrical and framing is finished.
-
Week of 19th -Plaster work continues this week. Monday and Tuesday plaster work concentrated in Painters and metalworkers. Plaster work will be finished by Wednesday.
-
Week of 26th - The lift will be installed this week. Plaster work continues, with finish trim and carpentry following as soon as the plaster is completed. Peter Bain Painting class moves to Seminar room this week.
-
The mechanical work will continue and will cause some disruption to the Ceramics area when they get their new air handler installed.
-
​
-
Week Oct- 19 Painters and Metalworkers studios -The lift will be installed this week.
-
Painters studio will be opened to construction until the unit is installed and doors in place. Painters activities moved to Seminar room.
-
Metals studio will experience noise while the lift work is in progress. No workers should need to access the metals space. Evening activities in the metals studio should be able to progress without interruptions.
-
-
November schedule will be posted later this week. Construction is expected to continue to Thanksgiving.
-
-
work to be done includes finish trim, Light installations and electrical finish, Painting and Floor finish.
​
​
-
-
Contact Louise Hara (Building Committee) with questions 978-287-4833 Lhara422@gmail.com
​
​